UPS-sen bijplaatsen On The Flight Jan Huntelaar: OpenText Manager Operations & Facilities EMEA Data Center Services Marco Wenzkowski: Business Development Manager Brown Field Projects
Royal HaskoningDHV Independent international engineering and project management consultancy 2
Market Leader in Enterprise Information Management (EIM) CEM Customer Experience Mgt CREATE EXCEPTIONAL CUSTOMER AND EMPLOYEE EXPERIENCES Web Content Management Customer Communication Management Media Management Digital Asset Management ECM Enterprise Content Mgt TRANSFORMING CONTENT FOR PRODUCTIVITY AND CONTROL Archiving Records Management Email Management File Archiving 3 3 Analytics DELIVER ANALYTICS FOR DATA-DRIVEN DECISIONS Business Network 1 2 3 4 5 6 INTELLIGENTLY AUTOMATE AND ORCHESTRATE BUSINESS AND CASE PROCESSES Fax and Document Distribution Cloud 7 8 based File Sharing Managed File Transfer Data Integration Discovery DISCOVER WHAT MATTERS SEARCH, EXTRACT, CLASSIFY, REVIEW, AND ANALYZE CONTENT ACROSS YOUR ENTERPRISE BPM Business Process Mgt INTELLIGENTLY AUTOMATE AND ORCHESTRATE BUSINESS AND CASE PROCESSES Dynamic Case Management Strategic Business Planning and
Market Leader in Enterprise Information Management (EIM) 1 2 3 4 5 6 7 8 4 4 https://www.youtube.com/?v=ip5cwsaxweo watch
UPS-en uitbreiden On The Flight 5
Opdracht Opentext wil graag hun UPS vermogen uitbreiden van 1x per feed naar 800kVA per feed in een live omgeving 6
Actuele situation 2N feed UPS-sen => 2 x Double conversion ; op de A feed en op de C feed; Actuele IT belasting < ; Bestaande UPS-sen uit 2010 en 2013 Autonomietijd tijd minimaal 20 minuten (@full load); Achter de UPS-sen zijn STS-sen en UPD (Ups Power Distribution) verdelers geïnstalleerd; 7
Gemaakte afspraken en kaders Installatie dient aan TIERIII van Uptime te voldoen; Indien bestaande UPS-sen hergebruikt worden, groot onderhoud kosten (begroot voor 2019) meenemen in het project; Gebruik maken van de bestaande batterijen? Project in bouwteam uitvoeren (OpenText installateur en RHDHV) Spanningsonderbreking / uitval IT apparatuur is geen optie! 8
Bestaande Single Line A feed C feed UPS A1 UPS C1 UOP A UOP C Bestaande installatie Nieuwe installatie STS A1 STS C1 9 UPD A1 UPD C1
Scenario #1 Verplaats UPS A1 naar C feed (UPS C2) Installeer 1 x 800kVA UPS op de A feed (UPS A) Installeer 2 x STS-sen (STS A2 and STS C2) Installeer 2 x UPD-s (UPD A2 and UPD C2) 10
Scenario #1 A feed C feed UPS A 800kVA UPS C1 UPS C2 (Oud A1) UOP A UOP C Bestaande installatie STS A1 STS A2 STS C1 STS C2 Nieuwe installatie UPD A1 UPD C2 11 UPD A2 UPD C1
Scenario #2 Verplaats UPS A1 naar C feed (UPS C2) Installeer 2 x UPS-sen op de A feed (UPS A1 en A2) Installeer 2 x STS-sen (STS A2 and STS C2) Installeer 2 x UPD-s (UPD A2 and UPD C2) 12
Scenario #2 A feed C feed UPS A1 UPS A2 UPS C1 UPS C2 (Oud A1) UOP A UOP C Bestaande installatie STS A1 STS A2 STS C1 STS C2 Nieuwe installatie UPD A1 UPD C2 13 UPD A2 UPD C1
Scenario #3 Installeer 4 x UPS op de A feed (UPS A1 en A2 / C1 en C2) Installeer 2 x STS-sen (STS A2 and STS C2) Installeer 2 x UPD-s (UPD A2 and UPD C2) 14
Scenario #3 A feed C feed UPS A1 UPS A2 UPS C1 UPS C2 UOP A UOP C Bestaande installatie STS A1 STS A2 STS C1 STS C2 Nieuwe installatie UPD A1 UPD C2 15 UPD A2 UPD C1
Evaluation Scenario omschrijving Capex / Opex 10y Voordelen Nadelen Weging 1=goedkoopste 1=1ste plaats 3=duurste 2=3de plaats #1 UPS A1 verplaatsten naar C2 Goedkoopste scenario 630A breakers op HVK zijn te klein/vervangen 1 x 800kVA UPS op de A feed Hergebruik bestaande batterijen Dikke kabels, weinig ruimte onder/boven vloer 1 2 x nieuwe STS-sen Fysiek verplaatsen van UPS A1 naar C2 3 2 x nieuwe UPD's Hergebruik van bestaande (oudere) apparatuur #2 UPS A1 verplaatsten naar C2 Hergebruiken 800A breakers op HVK Niet goedkoopste scenario mbt OPEX 2 x UPS-sen op de A feed Hergebruik bestaande batterijen Fysiek verplaatsen van UPS A1 naar C2 2 2 x nieuwe STS-sen Initieel ontwerp blijft behouden Hergebruik van bestaande (oudere) apparatuur 2 x nieuwe UPD's #3 4 x UPS-sen Alle apparatuur vernieuwd Verreweg duurste scenario 2 x nieuwe STS-sen Hergebruik bestaande batterijen Langste doorlooptijd 3 2 x nieuwe UPD's Initieel ontwerp blijft behouden 1 2 16
Opdracht met succes uitgevoerd 17
Contact Marco Wenzkowski Business Development Manager brown field projects En Asset Management M: +31 6 52698946 E-mail: marco.wenzkowski@rhdhv.com Jan Huntelaar OpenText Manager Operations & Facilities EMEA Data Center Services M: +31 6 20004794 E-mail: jan.huntelaar@opentext.com 18