North/South-line: The connection with tomorrow



Vergelijkbare documenten
Impacts Tallinn 31 st may 2018 Senta Modder - Germa Bakker

Stedelijke Ontwikkeling India


Internationale Ambities

A4Kwartier fase 2 RIJSENHOUT

13 juni2012 Kivi Niria. Abjan Jacobse Teamleider geotechniek(botlekbrug)

Project Update Community Meeting. October 29, 2009

Travel Survey Questionnaires

Free Electives (15 ects)

Drones for Firefighting. Friday

Alcohol policy in Belgium: recent developments

Designing climate proof urban districts

EFSI Info-session for the Flemish Region

Modern Land Consolidation in the Netherlands

PROJECT INFORMATION Building De Meerlanden Nieuweweg 65 in Hoofddorp

small urbanism urban development with a small scale

Notitie : In de grond gevormde palen met grondverwijdering

Cycling in The Netherlands & The Hague

Issues in PET Drug Manufacturing Steve Zigler PETNET Solutions April 14, 2010

Feedback WG System Operations 21 November 2012

Ghent Climate Proof City 2030

ASTRIN Lighting Interoperability Standard Het ALiS Protocol in de praktijk

For Sale & For Rent Gerdesiaweg Rotterdam-Kralingen, the Netherlands

Fidelity of a Strengths-based method for Homeless Youth

Bemalen en monumenten voorkomen van schade

Digital municipal services for entrepreneurs

Agenda: Rotary Industry Group

Continuous testing in DevOps met Test Automation

TE HUUR STAMMERHOVE 13 DIEMEN COLLIERS INTERNATIONAL REAL ESTATE B.V. TE HUUR STAMMERHOVE 13 - DIEMEN

TE HUUR MOLENWERF AMSTERDAM COLLIERS INTERNATIONAL REAL ESTATE B.V. TE HUUR MOLENWERF AMSTERDAM

HOPE UNIVERSITY COLLEGE ADDIS ABABA ETHIOPIA

Opportunities for Collaborative Interdisciplinary Programs. James W. Jones Director, FCI

B2Ai Human Centered Architecture

Talentmanagement in tijden van crisis

OVERZICHT VAN VISUALISATIES

Business as an engine for change.

9811 Borneodriehoek, Amsterdam Borneotriangle, Amsterdam

International Leiden Leadership Programme

P U B L I C A T I E S CRUX Engineering BV

Best Practise: Car Parks in Leiden Drs. Ing. J.N. de Koning

Fortifications of Antwerp

How will be the journey from corrective maintenance to preventive or even predictive maintenance?

Introduction Henk Schwietert

Dutch Construction Contracts: views from abroad

Developments in SWAT modelling

Aim of this presentation. Give inside information about our commercial comparison website and our role in the Dutch and Spanish energy market

Laboratory report. Independent testing of material surfaces. Analysis of leaching substances in treated wood samples conform guide line EU 10/2011

Opleiding PECB IT Governance.

Zuiveren met verstand. RFID tags als verklikkers in de afvalwaterzuivering. S.A.C. (Saskia) Hanneman Innovatietechnoloog Waterschapsbedrijf Limburg

Patiëntenparticipatie in

Safe production of Marine plants and use of Ocean Space. 2de Nederlands-Belgische Zeewierconferentie: DE MULTIFUNCTIONELE NOORDZEE

Adventures in GIS to Support LEED Certification. Karen Jordan

SHP-TS TwinArc SA SHP-TS 400W TWINARC E40 SL PRODUCT OVERVIEW

Gebruik van GRI-indicatoren voor interne sturingsprocessen. Mark van Rijn 14 October 2004

Betekenis nieuwe GRI - Richtlijnen. Rob van Tilburg Adviesgroep duurzaam ondernemen DHV Utrecht, 23 November 2006

Building with Nature in the Delta. Inzetten van natuur en natuurlijke processen voor medegebruik

What issues should the Province of Limburg address when developing its climate-proof policy?

Prove Everything or Die. Presentatie meetbaarheid Woensdag 9 mei 2012 Robin den Hoed

Reykjavikweg 2 SCHIPHOL ZUIDOOST

ARTIST. Petten 24 September More info:

Zutphen Groenmarkt >>>

Innovatie door samenwerken - Slim gebruik maken van de aanwezige informatievoorziening - September 2014

TE HUUR EMMASINGEL EINDHOVEN

Make a smart move+ WIJCHEN LOGISTICS CENTRE m 2 BEDRIJFSRUIMTE TE HUUR IN-HOUSE TECHNISCH EN VASTGOEDBEHEER AANTREKKELIJKE HUURVOORWAARDEN

End-to-End testen: de laatste horde

SURFnet User Survey 2006

Lelystad, Mainport Park A6

STORM Groep b.v. We will get there in time

Cateringweg 10, Schiphol

Business Architectuur vanuit de Business

underground container systems metro, chiplock and winconsyst

Open source VoIP Networks

Kwalitatieve Studie naar Motivatie en Barrières van Etnische Minderheden uit Amsterdam

Developing an adaptive, diagnostic test of. English writing skills

Risk & Requirements Based Testing

Big Data en Testen samen in een veranderend speelveld. Testnet 10 april 2014 Paul Rakké

FOD VOLKSGEZONDHEID, VEILIGHEID VAN DE VOEDSELKETEN EN LEEFMILIEU 25/2/2016. Biocide CLOSED CIRCUIT

Support Center GIS-Flanders

[ ] OVER ASCOM HARRY WASSENS, SALES DIRECTOR. Over Ascom Harry Wassens Ascom (Nederland) B.V.

Stephanie van Dijck De integrale aanpak maakt complexiteit hanteerbaar

Report for D-Sheet Piling 9.2

Topic 10-5 Meeting Children s Intellectual Needs

University of Groningen Educational value of digital examination

Smart Mobility. Marije de Vreeze Connekt / ITS

Mounting ceiling & wall

Creating a marketplace where expertise is made available through videoconferencing. Roland Staring Community Support Manager roland.staring@surfnet.

9301 Oldenelerbroek, Zwolle Oldenelerbroek, Zwolle

WP6 TenCompetence Assessment Specification v.1.0 and Proof-of-concept tools. Milen Petrov, Sofia University EDE 2007,

Dutch Research Council: women in scientific careers

SMART(ER) GATES Multi use and multi functional HUB s. ADVIER Mobiliseert, NIO Architecten en OKRA landschapsarchitecten

SAMPLE 11 = + 11 = + + Exploring Combinations of Ten + + = = + + = + = = + = = 11. Step Up. Step Ahead

0515 FOREIGN LANGUAGE DUTCH

0515 DUTCH (FOREIGN LANGUAGE)

STRESS CORROSION CRACKING OF WELDED JOINTS OF Al-Mg ALLOYS

Profile visitors NRC Q

Utch PO. Net innovations Dutch demersal fleet. Urk, 1 October 2015 Durk van Tuinen Cooperative Fisheries Organization

Engineering Services for Additional Studies and Technical Assistance for New Locks PANAMA

Enable all people to travel by plane


0021 Brede School, Amsterdam - Osdorp Community School, Amsterdam - Osdorp

Transcriptie:

North/South-line: The connection with tomorrow 1

The north/south line 1. Introduction 2. Tecnics 3. Organisation Break 4. Risk management 5. Current status 6. Questions and possible answers 2

North/south line 2. Tecnics Why a North/South-line The city Alignement construction techniques Stations Monitoring Safety sytems 3

North South line: part of a regional system 4

North/Southline: Part of the local public transport system 5

Travelling speed of public transport systems V(traveler) [km/hour] CITY (dense grid) Busses & streetcars 12 18 REGION City environment : metro 35 Region : bus > 35 PROVINCE Train 50 60 LAND Intercity trains > 60 6

Gemeente Amsterdam North/Southline: stations 7

2011 without North/South line 8

2011 with North/South line 9

The North/South-line: horizontal alignment In situ TBM In-situ Submerged tunnel In-situ surface construction South Inner-city North 10

North Construction: Tracks & Stations at surface level. Shallow insitu built tunnel 11

Inner city Submerged tunnel Caissons Twin bored tunnels Deep stations (cut & cover) 12

South Twin bored tunnels Deep station (cut & cover) Shallow station (cut & cover) In-situ tunnels 13

Construction methods 14

Central Station : 1890 15

Central Station : actual situation 16

Central Station: 2011 17

5 Station Geb. IJ-zijde Emplacement NAP -5 Ophoogzand -10-15 Klei zandhoudend IJ-klei -20-25 -30 Zand weinig silthoudend Eemklei 18

19

Central Station:submerged tunnel 20

Gemeente Amsterdam

25

26

27

Cut & Cover building pits 28 28

Station Rokin 29

Station Rokin : entrances 30 30

Station Rokin: platform 31

South, vertical alignment 32

Ferdinand Bolstraat 33

Station Ceintuurbaan 34

Station Ceintuurbaan 35

Environment: monitoring (early warning) 36

The North/South-line Amsterdam 3. Organisation Project organisation 37

Gemeente Amsterdam Organisation Organogram Projectoffice Noord/Zuidlijn Director (1 fte) Manager Communicatiion (1 fte) Head Stafoffice / Projectsecretaris (1 fte) communication-adviser (1 fte) office manager (1 fte) projectsecretary (2 fte) juridical assistant (1 fte) city board assistant (1 fte) Manager Finance & Planning (1 fte) controller (2 fte) General Construction Manager (0,7 fte) Manager Suurounding (1 fte) Constructionmanager Cluster A (1 fte) Construction manager Cluster B (1 fte) Construction manager Cluster C (1 fte) Construction manager Cluster D (1 fte) Projectleader surrounding projects (1 fte) Constructioncoordinator surrounding (1 fte) Head Projectcontrol (1 fte) projectcontrol (3 fte) secretary (1 fte) 38

Gemeente Amsterdam Organisation Constructionmanagement Projectoffice Noord/Zuidlijn Contractmanagement Consultantoffice Noord/Zuidlijn Director projectoffice Head Consultingoffice General Constructionmanager General Contractmanager Constructionmanager Cluster A Constructionmanager Cluster B Constructionmanager Cluster C Constructionmanager Cluster D Contractmanager Cluster A Contractmanager Cluster B Contractmanager Cluster C Contractmanager Cluster D Relatie Projectbureau - Adviesbureau 39

Gemeente Amsterdam Organisation Control each contract Constructionmanager PB Contractmanager AB Head Daily Control AB Contractor 40

Gemeente Amsterdam Organisation Structure of organisation: Board <-> PO: alderman staff board team PO <-> Consultant office: general contract meetings Construction Manager<->Contract Manager Consultant Office <-> contractor construction meeting 41

The North/South-line Amsterdam Break 42

The North/South-line Amsterdam 4. Risk management Topics Analyzing risks Reducing risks Testing Contract filosofy TBM Environment Monitoring No insurance CAR 43

The North/South metroline Amsterdam Risk perception Risk management Risk analysis 44

The North/South metroline Amsterdam Topics: The project The start: analyzing the risk profile Reducing the risk profile Environment (surroundings) Actual situation (contractors) 45

The Project: 200.000 passengers / day 9 km long new infrastructure 6 km subsurface 4 complex deep stations 2x4 km single track twin bored tunnels in operation: 2011 46

Overview of the construction methods caissons Submerged tunnel In situ tunnel Twin bored tunnels In situ tunnel Level South Inner City North 47

ANALYZING THE RISK PROFILE Focus on Inner city. Use of TBM in the city of Amsterdam Deep stations Passage of the Central Station 48

REDUCING THE RISK PROFILE Goal (1994): The risk profile of the construction of the North/South metro line should be less or equal to a substantial traditional project Actual situation (2003): General consensus that this goal is achieved 49

REDUCING THE RISK PROFILE Risk analysis & management: Design Organization Contracts Investing > 100 million in risk reducing measures 50

REDUCING THE RISK PROFILE Design: Horizontal alignement follows street pattern. Vertical alignement bored tunnels determined to avoid obstacles. Carefull choice of station location. 51

REDUCING THE RISK PROFILE Design: Development of design tools Design by testing Investigations (soil & buildings) Mitigating measures 52

REDUCING THE RISK PROFILE Investing [million] Soil investigation 3 Building investigation 3 Foundation reconstruction 20 (30%) Monitoring system 15 Mitigating measures 40 Research & design by testing 15 etc. Deep stations Passage of the Central Station 53

Design by testing: why? 54

4D FEM model TBM & subsurface 55

TBM driven track tunnels & pile foundations 56

GEO-GIs FSPT FSIT TBM / TVIT Design by testing (Full scale tests) 3D-EEM Monitoring Lining test IBCS 57

OVERVIEW FULL SCALE TESTS Influence TBM on pile foundations Vibration behavior tunnellining & pile foundations Slurry wall Tail void injection [1:5] Soil treatement tests Use of drilled steel piles to large depths Use of large diametre steel piles in limited space Compensating Grouting trail 58

DEEP STATIONS : Ceintuurbaan 59

FULL SCALE SLURRY WALL TEST 60

CONSTRUCTION TECHNOLOGY Generating knowledge: Buildings Pile foundations Soil TBM process 61

FULL SCALE PILE TEST 62

FULL SCALE PILE TEST 63

CONSTRUCTION TECHNOLOGY 64

Full scale tests. Lining test Soil freezing Slurry wall test 65

Full scale tests. Tail void injection Tubexpile test Large diameter pile test Compensating Grouting Trail Soil treatment tests 66

FULL SCALE SOIL TREATEMENT TEST 67

FULL SCALE SOIL TREATEMENT TEST 68

TAIL VIOD INJECTION TEST [1:5] 69

SINGLE TRACK BORED TUNNELS Diameter 7 [m] Second sand layer Street pattern 70

71

Application of results. 72

REDUCING THE RISK PROFILE Organization. Fit for purpose (flexible) Management with technical expertise First, second & third opinions Making use of experience generated at other projects (site visits, trails) 73

Contractfilosofy TBM E/C- contract: Detail design of lining Detail mitigating measures design TBM Target price: Contractor price: part fixed, part variable Incentives Basic risc spread (BRT) 74

DIRECT COSTS (FIXED) DIRECT COSTS (VAR.) TARGET LOCATIONCOSTS GENERAL COSTS BASIC PROFIT TARGET & RISKS RISK CONTRACTOR RISK CITY. RISK FUND 75

DIRECT COSTS (FIXED) = INCENTIVE TARGET DIRECT COSTS (VAR.) LOCATION COSTS GENERAL COSTS BASIC PROFIT COST REDUCTION 1 2 TARGET & RISKS RISICO OPDRACHTG. 4 3 RISK CITY 76

REDUCING THE RISK PROFILE Contracts. Philosophy: 13 main contract clusters Contract form: E/C & (modified) RAW Contract attitude: Risk sharing & risk bearing Responsibility Trust 77

ENVIRONMENT Historical buildings: Assesment of condition Developement of settlement limits Mittigation measures Early warning system (monitoring) 78

ENVIRONMENT Lackof(public) space: Choice of construction methods Phased construction Construction of additional space 79

ENVIRONMENT Inhabitants: Communication Central claim office 80

MONITORING SYSTEM Base monitoring Early warning system Contract control Assurance Civil law 81

FOUNDATION INSPECTION 82

Pile plan Massive bearing wall Façade wall 1.2m 18m 7m Connection of piles with masonry walls Masonry walls Pile group 2 wooden piles average dia. 180mm 83

FOUNDATION INSPECTION 84

MITIGATING MEASURES Three types of mitigating measures: Foundation renovation Real time compensating grouting Compensating settlements by hydraulic jacks 85

COMPENSATING GROUTING 86

HYDRAULIC JACKING Munt Tower 87

ACTUAL SITUATION Most complex parts tendered 6 out of 7 contracts awarded: Contractors are known Participation of the contractors in detailled design started Foundation renewal in progres Monitoringsystem working 88

Q & A: After the break 89